Takeaway: Plan sets require comprehensive on-site data, including measurements of every roof plane, internal surveying analysis, and details regarding any niche AHJ or utility rules. Designing plan sets in-house can be valuable, especially for ultra-complex projects and when local regulation knowledge is key. Outsourcing plan set creation to a trusted third party means quick (< 48-hour) turnaround times and more opportunity to flex up and down as your team needs change.
A “good,” comprehensive plan set enables a design process that yields no revisions, permitting delays, or install-day call-offs. These are all essential as the solar industry grows, yet 66% of Designers have to deal with revisions on a regular basis. Quality-focused Contractors consistently balance speed with quality, attempting to maximize their team’s resources.
Bad plan sets, on the other hand, are rife with small omissions and errors that contradict AHJs, contrast with utility regulations, and make things difficult for Procurement and Installers. These often lead to many of the revisions Designers face.
Here are the characteristics of each—and how to avoid the costly problems caused by a bad plan set.
What makes a good plan set?
A good plan set is one that Engineers can easily compile and stamp so Procurement can order what they need and Installers know exactly what’s going to fit on install day.
That requires a few elements:
Property overview: | |
---|---|
|
Electrical information: | |
---|---|
|
Array plan: | |
---|---|
|
Stamps and placards: | |
---|---|
|
Additional needs: | |
---|---|
|
And, of course, do a quick grammar and spell-check on the plan set before submitting it. This is less about catching small typos and more about ensuring all technical components are labeled correctly and details are easy to understand for Procurement, Installers, AHJs, and utilities.
All of this information is best collected by (1) a drone to capture the external / roof data, and a mobile app for internal information, specifically digitizing electrical and structural data.
Where plan sets can go wrong
Here’s how a bad plan set happens:
Limited upfront information: As the saying goes, “garbage in means garbage out.” Designers need accurate, comprehensive on-site information, and 86% say that incorrect data from manual survey methods is the leading cause of errors, revisions, and delays. Roof climbs, tape measures and paper and pencil just don’t scale in an operationally efficient way.
Not factoring AHJ requirements into plan set templates: Sometimes requirements will change how you present information, so make sure you create new templates for each AHJ you work with.
Unclear language: If something is mislabelled or isn’t presented in the specific way that an AHJ or utility needs, it’s more likely that you’ll get a kickback or revision request.
Not updating plan set templates: Mistakes or omissions can happen, but it becomes a real problem if you don’t update templates to avoid making the same mistake twice. When you update templates, make sure you’re not inadvertently causing other problems by changing a separate piece of the plan set.
How plan sets get made
Plan sets can be produced in-house or through a third-party partner.
Working in-house provides the opportunity to be incredibly detailed or handle niche and complex projects. However, in-house design teams can be expensive to maintain, may limit the types of projects you can take on, and just take longer.
On the other hand, outsourcing delivers quick results (less than 48 hours), but it may take some extra leg work to design templates for highly specific AHJ use cases. It can also be hard to pivot quickly or develop incredibly granular outcomes for certain projects. However, even with these potential challenges, outsourcing is often far more efficient.
“Drafting in-house took much longer,” said Ethan Goddard, VP of Energy Technology at Solar Energy Services. “The turnaround time [with Scanifly Design Services] is tremendous.”
The importance of an experienced plan set team
Whether in-house or outsourced, the key to success at the start will be setting up initial templates and being keenly aware of local rules.
For an outsourced design team make sure you over-communicate system requirements up front; include all local AHJ requirements and other details to avoid downstream issues. Then be available to address any mistakes or issues as they happen, updating templates as needed to ensure a scalable and consistent process.
If you’re curious to try out a third-party partner, work with Scanifly Design Services on a new project or one you’ve already completed, to compare results and quality.