Solar Power World

  • Home
  • Top Solar Contractors
  • Articles
    • Most Recent Posts
    • News
      • Latest News Items
      • SPW State News Hub
      • IRA coverage
      • Solar tariffs
      • U.S. manufacturing updates
    • Featured
      • Latest Feature Stories
      • Contractor’s Corner
      • Trends in Solar
      • The Solar Explorer
  • Policy
    • The Solar Policy Scoop
    • IRA Coverage
  • Markets
    • Residential
    • Commercial
    • Community Solar
    • Utility
  • Products
    • Winners of SPW’s 2024 Top Products
    • Batteries and Storage
    • Electric Vehicle (EV)
    • Inverters
      • U.S. solar inverter manufacturers
    • Racking and Mounting
      • U.S. solar mounting manufacturers
    • Software
    • Solar Panels
      • U.S. solar panel manufacturers
  • Resources
    • About SPW
    • Digital Issues
    • Event Coverage
    • Podcasts
    • Product Manufacturing Locations
      • U.S. solar inverter manufacturers
      • U.S. solar mounting manufacturers
      • U.S. solar panel manufacturers
    • Solar Classrooms
    • Suppliers
    • Videos
    • Webinars / Digital Events
    • Whitepapers
    • Voices
  • 2025 Leadership
    • 2024 Winners
    • 2023 Winners
    • 2022 Winners
  • Advertise
  • Subscribe

Vistra retiring coal plants, breaking ground on 6 solar projects

By Billy Ludt | September 29, 2020

Share

Texas-based energy company Vistra plans to accelerate its transition to clean power generation sources and advance efforts to significantly reduce its carbon footprint. The company launched Vistra Zero, a portfolio of zero-carbon power generation facilities, which includes seven new developments — some solar, solar + storage and standalone energy storage — in its primary market of ERCOT that total nearly 1,000 MW.

In addition, Vistra established further long-term emissions reduction targets, released its first climate report and announced its intention to retire all of its generation subsidiaries’ coal plants in Illinois and Ohio.

“The aggregate impact of these milestone initiatives is clear: Vistra’s commitment to our transformation to a low-to-no-carbon future is unequivocal and offers unique opportunities for growth and innovation,” said Curt Morgan, president and CEO of Vistra. “As evidenced by the actions we take and investments we make, Vistra is paving its way for a sustainable future — economically and environmentally — and we’ve been focused on transitioning our generation portfolio for the benefit of the environment, our customers, our communities, our people and our shareholders.

“Importantly, Vistra’s leadership on these issues will not impact our core mission to provide consumers with reliable, affordable, and sustainable energy while lowering emissions,” Morgan continued. “Electricity is an essential resource, and the demand for it will continue to grow as climate initiatives are implemented and the economy is further electrified. So, while the way we produce electricity is changing, our essential role in the process and core mission will not. Vistra is well-positioned to not only prove our resiliency during this important transformation to cleaner generation sources, but to lead the way. Our value proposition has never been stronger, and our sustainability has never been clearer.”

New Zero-Carbon Development Projects: Vistra Zero

Vistra, which is developing the 400-MW/1,600-MWh Moss Landing Energy Storage Facility in California, is breaking ground on six new solar projects and one energy storage project. These new zero-carbon developments, represent a capital investment of approximately $850 million and are all located in the Texas ERCOT market.

2021 projects

  • Andrews Solar Facility, Andrews County, 100 MW
  • Brightside Solar Facility, Live Oak County, 50 MW
  • Emerald Grove Solar Facility, Crane County, 108 MW
  • Upton 2 Solar and Energy Storage Facility, Phase III, Upton County, 10 MW solar — bringing its total solar capacity to 190 MW

2022 projects

DeCordova Energy Storage Facility, Hood County, 260 MW/260 MWh. Co-located on the site of Luminant’s natural gas-fueled DeCordova Power Plant

  • Forest Grove Solar Facility, Henderson County, 200 MW
  • Oak Hill Solar Facility, Rusk County, 200 MW
  • The Vistra Zero portfolio also includes the company’s existing nuclear, renewable and energy storage facilities:
  • Comanche Peak Nuclear Power Plant (2,300 MW)
  • Upton 2 Solar (180 MW) and Energy Storage Facility (10 MW/42 MWh)
  • Moss Landing Energy Storage Facility (400 MW/1,600 MWh) – 300 MW Phase I expected online December 2020; 100 MW Phase II expected online by August 2021
  • Oakland Energy Storage Facility (36.25 MW/ 145 MWh) – expected online January 2022

Vistra continues to evaluate additional solar and battery projects, including more than 1,000 MW in Texas, more than 1,000 MW in California and approximately 450 MW in Illinois under the Coal to Solar and Energy Storage Act. Vistra is also exploring potential future development opportunities at many of the company’s existing power plant sites.

Updated 2030/2050 Emissions Reduction Targets

Consistent with its strategic priorities, the company also accelerated its greenhouse gas emissions reduction targets. Vistra is now setting out a 60% reduction, up from 50%, in CO2 equivalent emissions by 2030 as compared to a 2010 baseline, and a long-term objective to achieve net-zero carbon emissions, up from an 80% reduction target, by 2050.

CO2 Reductions Through Coal Retirements

Vistra also announced its next phase of coal plant closures in Illinois and Ohio. The company expects to retire seven Luminant power plants, of which the company owns a combined capacity of more than 6,800 MW, between 2022 and 2027.

Since the company’s leadership change in 2016, Vistra and its subsidiaries have closed or announced the closure of 19 coal plants totaling more than 16,000 MW across Texas, Pennsylvania, Ohio, Illinois and Massachusetts. In total, Vistra and its subsidiaries have now retired or announced the retirement of more than 19,000 MW at 23 coal and natural gas plants since 2010.

Vistra’s Climate Report

A review of Vistra’s climate strategy is contained in Vistra’s first “Climate Report“. Among other topics, the climate report discusses various climate-related risks and opportunities that Vistra management has identified as influencing the company’s long-term strategy.

News item from Vistra

About The Author

Billy Ludt

Billy Ludt is senior editor of Solar Power World and currently covers topics on mounting, installation and business issues.

Comments

  1. Solarman says

    September 29, 2020 at 11:53 pm

    I see the Moss Landing project phase I and phase II but see no mention of the Elkhorn project which is supposed to be 1,500MW/6,000MWh using TESLA Mega Packs, about 2,000 of them. I’ve come across some articles that say Elkhorn is ‘approved’ already. So, did Dynegy or Vistra back out of the Elkhorn deal and PG&E is still saying TESLA and Elkhorn are a go.

    Reply

Tell Us What You Think! Cancel reply

Related Articles Read More >

Prysmian releases all-in-one utility solar cabling package at Cleanpower 2025
More commercial and community solar projects financed through TPO in 2024
Affordable Wire Management unveils cabling solution for utility-scale energy storage projects
JinkoSolar establishes first state-approved solar panel recycling takeback program in Washington
Solar Power World Digital Edition
Check in with the nation's leading solar construction magazine today.
 
“the-informed-solar-installer”
“solar
“spw
EXPAND YOUR KNOWLEDGE AND STAY CONNECTED
Get the latest info on technologies, tools and strategies for Solar Power Professionals.

Contractor’s Corner Podcast

“solar
Solar Power World
  • Top Solar Contractors
  • Solar Articles
  • Windpower Engineering & Development
  • Leadership
  • About/Contact Us
  • Subscribe
  • Advertising
  • WTWH Media

Copyright © 2025 WTWH Media LLC. All Rights Reserved. The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of WTWH Media
Privacy Policy | RSS

Search Solar Power World

  • Home
  • Top Solar Contractors
  • Articles
    • Most Recent Posts
    • News
      • Latest News Items
      • SPW State News Hub
      • IRA coverage
      • Solar tariffs
      • U.S. manufacturing updates
    • Featured
      • Latest Feature Stories
      • Contractor’s Corner
      • Trends in Solar
      • The Solar Explorer
  • Policy
    • The Solar Policy Scoop
    • IRA Coverage
  • Markets
    • Residential
    • Commercial
    • Community Solar
    • Utility
  • Products
    • Winners of SPW’s 2024 Top Products
    • Batteries and Storage
    • Electric Vehicle (EV)
    • Inverters
      • U.S. solar inverter manufacturers
    • Racking and Mounting
      • U.S. solar mounting manufacturers
    • Software
    • Solar Panels
      • U.S. solar panel manufacturers
  • Resources
    • About SPW
    • Digital Issues
    • Event Coverage
    • Podcasts
    • Product Manufacturing Locations
      • U.S. solar inverter manufacturers
      • U.S. solar mounting manufacturers
      • U.S. solar panel manufacturers
    • Solar Classrooms
    • Suppliers
    • Videos
    • Webinars / Digital Events
    • Whitepapers
    • Voices
  • 2025 Leadership
    • 2024 Winners
    • 2023 Winners
    • 2022 Winners
  • Advertise
  • Subscribe