On September 24, the California Public Utilities Commission (CPUC) issued sweeping changes to Rule 21, the rules under which distributed energy resources, like solar power and energy storage, may interconnect to California’s electric grid. The changes represent a radical shift in how states handle interconnection policy, with a number of unprecedented changes that will provide a model regulators in other states can look to as they work to enable more renewable energy on the grid through modern interconnection policies.
The Interstate Renewable Energy Council (IREC) was deeply involved in developing and advocating for many of the changes adopted and commends these efforts by the CPUC.
“IREC applauds the CPUC’s recent updates to Rule 21, which significantly modernize California’s energy policy and pave the way to more rapidly deploy large amounts of clean energy — critical to meeting the state’s climate commitments and increasing resilience,” said IREC president and CEO Larry Sherwood. “Today’s changes are a major milestone that represent the culmination of many years of work. IREC has been engaging on Rule 21 since 2011 and has been involved in almost every major innovation, including helping to develop California’s Integration Capacity Analysis, which today’s decision puts into use in improving the interconnection process.”
Interconnection to the electric grid is a critical step in the deployment of most renewable energy systems, including solar power and energy storage systems. Yet lengthy processes for interconnection approval that rely on outdated technologies can often be a barrier in the process. The updates to Rule 21 announced by the CPUC have been years in the making and introduce several never-before-implemented advances that will significantly improve the process for adding more renewable energy to the grid.
The revisions to Rule 21 encompass many issues but three of the most noteworthy include:
- The plan to incorporate data on the actual grid conditions at the locations of projects that request to interconnect;
- an option for developers to propose project operating schedules that are based on those grid conditions; and
- the addition of more advanced interconnection policies for interconnection of energy storage projects.
One of the most impactful changes is the incorporation of data on grid conditions into the interconnection process. Under the changes approved by the CPUC, California utilities will begin to use Integration Capacity Analysis results when making interconnection decisions. Integration Capacity Analysis (ICA), called hosting capacity analysis in other states, is a process of modeling the electricity grid to determine the conditions on a utility’s distribution grid that impact its ability to host additional distributed energy resources (DERs), like solar or energy storage, at specific locations without the need for costly upgrades and/or lengthy interconnection studies.
“ICA is a revolutionary leap forward in grid transparency, in terms of providing customers, developers, and regulators with truly useful, accessible and in-depth distribution grid information” said Sky Stanfield, partner at Shute, Mihaly & Weinberger who represents IREC in clean energy regulatory proceedings, including the Rule 21 revision process. “This first-ever incorporation of ICA in the interconnection process is a key milestone that has the potential to reduce the guessing game in selecting interconnection locations and to vastly improve the process for clean energy customers and developers. Building upon this, another important change to Rule 21 provides a means for project developers to take ICA results into account in order to avoid costly grid infrastructure upgrades that could make their project financially infeasible.
Specifically, project developers will be able to propose operating schedules for their projects that are tailored to the grid conditions at their project location. For example, an applicant could propose to export more energy when it supports the grid, like during California’s recent heat waves, and to curtail the energy produced by a solar project when it would stress the grid, such as in months with less energy demand. This will significantly benefit the grid, reduce the need for expensive upgrades, and lower the costs of DER deployment.
Finally, the updates to Rule 21 also provide guidance for the interconnection of energy storage projects to the grid. This is significant because energy storage has a number of unique characteristics compared to other DERs like solar. In particular, energy storage systems can be designed with the capability to limit or prevent the export of energy onto the grid altogether.
This new rule provides much needed clarity for these “limited export” systems and will increase access to lower-costs methods for controlling export. It also includes the use of the most recent test standard for power control systems issued by UL. As California grapples with unprecedented climate change impacts, from wildfires to heat waves, providing pathways to deploy more renewable energy and energy storage faster and when it is most needed will help the state transition to a lower-carbon, more resilient grid. With these changes to Rule 21, California regulators have set a new standard for modern interconnection policies that will support this goal.
News item from IREC
Mark Stout says
This is a step in the right direction. As California goes, so goes the nation. California has a unique opportunity to design a smart grid infrastructure sorely needed nationally. California, Arizona, and Nevada combined have enough area to host wind and solar farms that could produce enough energy to power the entire U.S. while storing that energy and making it available to a national smart grid that can send the stored electricity to any public or municipal utility company in the U.S. on demand, and have this be managed by a government agency, maybe modeled after CalISO or something similar, but operated by private companies who are answerable to a national board of that government agency. In conjunction with this, the existing buildings in the U.S. need to be retrofitted to reduce their energy use to come as close to Zero Net Energy (ZNE) with electrification as they can reasonably get with new construction being built to be ZNE.
Training for these jobs would take one to two weeks and create millions of jobs. This national undertaking would offset all the job losses caused by ending subsidies for fossil fuel industries exploration and production and growing the jobs in the energy efficiency, renewable energy, and energy storage.
Solarman says
““ICA is a revolutionary leap forward in grid transparency, in terms of providing customers, developers, and regulators with truly useful, accessible and in-depth distribution grid information” said Sky Stanfield, partner at Shute, Mihaly & Weinberger who represents IREC in clean energy regulatory proceedings, including the Rule 21 revision process. “This first-ever incorporation of ICA in the interconnection process is a key milestone that has the potential to reduce the guessing game in selecting interconnection locations and to vastly improve the process for clean energy customers and developers. Building upon this, another important change to Rule 21 provides a means for project developers to take ICA results into account in order to avoid costly grid infrastructure upgrades that could make their project financially infeasible.””
IF a utility Engineering group determines where and how much energy storage needs to be constructed along the grid, then placing the energy storage strategically along the grid, the asset can be used to stack grid services to amortize this asset sooner than later. A side advantage, as more R&D is committed to battery storage systems, new chemistries may come along and can replace existing storage with more cost effective energy storage as progress is made.